TORONTO, Feb. 21 /CNW/ - Agnico-Eagle Mines Limited announced today that
probable gold reserves at its Suurikuusikko gold project in northern Finland
total 2.3 million ounces. Previously, only measured and indicated resources
had been defined on the property. The Suurikuusikko project was acquired
through the acquisition of Riddarhyttan Resources AB in 2005.
Highlights of the Suurikuusikko Project
- 2.3 million ounces of probable gold reserves from 13.8 million tonnes
grading 5.3 grams per tonne
- Measured and indicated resource contains 1.9 million tonnes grading
4.2 grams per tonne, or 252,000 ounces of gold.
- Inferred resource contains 6.7 million tonnes grading 4.4 grams per
tonne, or 934,000 ounces of gold.
- Feasibility study nearing completion. Contemplates 3,000 tonne per day
mining scenario, initially from open pit, transitioning to underground
- Capital expenditures expected to be approximately $170 million
- Large, prospective, land position comprising 6,475 hectares. Known
strike length of the gold bearing structure is 15 kilometres, with
only 5 kilometres drilled so far
"Agnico-Eagle is proud to be expanding into Finland, a country in which
there is a long history of mining. Also, the large new gold reserve and
resource at Suurikuusikko remains open for further expansion," said Sean Boyd,
Vice-Chairman and Chief Executive Officer. "Our feasibility study is nearing
completion and a production decision is anticipated in the second quarter of
this year," added Mr. Boyd.
The Suurikuusikko Property
On November 9, 2005, Agnico-Eagle announced the successful closing of a
share exchange offer to acquire the remainder of the shares of Riddarhyttan
that it did not already own. The principal asset of Riddarhyttan was a 100%
interest in the Suurikuusikko gold property in the Lapland area of northern
Finland.
Suurikuusikko is situated approximately 50 kilometres from the
municipality of Kittila, a community of 5,000 thousand people, located 900
kilometres north of Helsinki. The property is comprised of a total of 83
tenements covering a surface area of 6,475 hectares. It was originally
discovered in 1986 by the Geological Survey of Finland. Riddarhyttan
successfully acquired the property in 1998 through a public tender process.
The known strike length of the gold bearing structure is 15 kilometres,
with only 5 kilometres drilled so far, providing the potential for the
discovery of additional gold bearing zones.
For a location map of Suurikuusikko, please follow the link below.
http://www.agnico-eagle.com/suuripropertymap.php
The Exploration Program - Potential For Further Reserve and Resource
Growth
The Suurikuusikko deposit is hosted by a north-south oriented shear zone
containing multiple mineralized lenses, which have been traced over a strike
length of 15 kilometres. Most of the work has been focused on the 4.5
kilometres which host the known gold reserves and resources.
From north to south, the zones are Rimminvuoma, North Rouravaara, Central
Rouravaara, Main East, Main West, Etela and Ketola. The Main West and East
zones host approximately 83% of the probable gold reserve estimate. Most of
the focus of the recent work has been on the Main and Rouravaara Zones. Up to
the end of December 2005, a total of 555 drill holes, comprising 157,238
metres of diamond drilling, were completed on the property.
Since the beginning of the year, eight drills have been in operation on
the property, five on resource conversion, two on exploration drilling, and
one on condemnation drilling required for the feasibility study.
The Main West and East Zones
The last drilling results were reported by Riddarhyttan in August 2005.
Some of the highlights from the holes drilled in the Main zones since that
time have been tabulated below:
<<
-------------------------------------------------------------------------
Gold (g/t)
True (cut to
Drill Hole Thickness(m) From(m) To(m) 50 g/t)
-------------------------------------------------------------------------
Main West Zone
--------------
-------------------------------------------------------------------------
SUBH 5046 4.7 447.0 454.0 6.7
-------------------------------------------------------------------------
SUBH 5060 6.9 668.0 678.6 5.0
-------------------------------------------------------------------------
SUBH 5069 3.1 470.0 475.0 8.5
-------------------------------------------------------------------------
SUBH 5078 7.3 476.0 486.0 7.9
-------------------------------------------------------------------------
SUBH 5103 15.3 407.6 434.1 4.7
-------------------------------------------------------------------------
Main East Zone
--------------
-------------------------------------------------------------------------
SUBH 5046 7.4 429.1 440.4 3.8
-------------------------------------------------------------------------
SUBH 5060 2.5 643.0 647.0 10.2
-------------------------------------------------------------------------
SUBH 5069 17.2 427.4 455.9 5.6
-------------------------------------------------------------------------
SUBH 5090 22.3 414.9 446.9 8.1
-------------------------------------------------------------------------
SUBH 5098 20.0 300.6 330.5 5.8
-------------------------------------------------------------------------
The Main West and East zones have been traced over a horizontal distance
of 1.5 kilometres and a vertical depth of approximately 800 metres below
surface. Most of the converted reserves are located within the Main zones,
which are known to contain at least three, roughly parallel, gold bearing
lenses.
It is these types of parallel zones, which require additional drilling
either from surface or underground, that contribute to the additional
potential of the property. The drilling continues to confirm a northern plunge
which is open for further expansion at depth and to the north.
The Main zones are currently the focus of mine planning for an open pit
and underground mine as part of the feasibility study. Over 600,000 ounces of
the gold reserves are located in the proposed open pit. This study is expected
to be completed in the second quarter of 2006.
The Central and North Rouravaara Zones
The Central and North Rouravaara zones have been the focus of much of the
exploration drilling over the past year and have developed into significant
gold zones, in terms of tonnage, grade and exploration potential. Drilling has
confirmed that they have similar characteristics as the Main zones, in that
they also contain several, roughly parallel, gold bearing zones. The
Rouravaara zones have been traced over a strike length of 500 metres and down
to a depth of approximately 500 metres below surface. Parts of the Rouravaara
zones have been characterized by significant thicknesses and potentially
higher grades than the Main zones. Some of the most recent drilling results
have been highlighted below:
-------------------------------------------------------------------------
True
Drill Hole Thickness(m) From(m) To(m) Gold (g/t)
-------------------------------------------------------------------------
Central Rouravaara Zone
-----------------------
-------------------------------------------------------------------------
SUBH 5066 31.5 360.8 408.0 5.5
-------------------------------------------------------------------------
SUBH 5073 12.0 515.0 534.3 9.4
-------------------------------------------------------------------------
SUBH 5081 22.3 296.7 340.3 5.1
-------------------------------------------------------------------------
SUBH 5104 27.7 343.6 391.2 6.1
-------------------------------------------------------------------------
North Rouravaara Zone
---------------------
-------------------------------------------------------------------------
SUBH 6001 11.4 583.7 599.2 3.1
-------------------------------------------------------------------------
The latest drill hole SUBH 6001 was significant as it is the northernmost
intersection to date, the deepest on the northern section of the Rouravaara
North zone. This result suggests that this zone is open in all directions at
depth.
The latest drilling on both the Main and Rouravaara zones continue to
confirm the upside potential of the entire Suurikuusikko gold structure. The
drilling over the past 18 months has continued to grow the deposit and provide
a better understanding of the geological controls. For 2006, Agnico-Eagle will
continue to drill with the seven exploration drills presently on site. The
program will continue on resource conversion; testing the deposit at depth,
and along strike, especially towards the north. An underground exploration and
development program is currently being considered as part of the feasibility
study.
For a longitudinal section and surface deposit plan of Suurikuusikko,
please follow the link below.
http://www.agnico-eagle.com/suurilongsection.php
For a geology plan of Suurikuusikko, please follow the link below.
http://www.agnico-eagle.com/suurigeologymap.php
Large And Expanding Gold Reserves And Resources
All of the drill results up to the end of January, 2006 were incorporated
into the latest mineral reserve and resource estimate.
Cautionary Note to U.S. investors concerning estimates of Measured and
Indicated Resources. This section uses the terms "measured" and "indicated
resources." We advise U.S. investors that while those terms are recognized and
required by Canadian regulations, the U.S. Securities and Exchange Commission
does not recognize them. U.S. investors are cautioned not to assume that any
part or all of mineral deposits in these categories will ever be converted
into reserves. Cautionary Note to U.S. investors concerning estimates of
Inferred Resources. This section also uses the term "inferred resources." We
advise U.S. investors that while this term is recognized and required by
Canadian regulations, the U.S. Securities and Exchange Commission does not
recognize it. "Inferred resources" have a great amount of uncertainty as to
their existence, and great uncertainty as to their economic and legal
feasibility. It cannot be assumed that all or any part of an Inferred Mineral
Resource will ever be upgraded to a higher category. Under Canadian rules,
estimates of Inferred Mineral Resources may not form the basis of feasibility
or pre-feasibility studies, except in rare cases. U.S. investors are cautioned
not to assume that part or all of an inferred resource exists, or is
economically or legally minable.
Agnico-Eagle's work has essentially confirmed previous estimates and
resulted in the initial conversion of resource into gold reserves. A summary
follows:
-------------------------------------------------------------------------
Contained gold Gold Grade Tonnes
(000's ounces) (g/t) (000's)
-------------------------------------------------------------------------
Probable Reserve 2,325 5.26 13,757
Measured and Indicated Resource 252 4.19 1,870
Inferred Resource 934 4.35 6,688
-------------------------------------------------------------------------
Feasibility Study Nearing Completion
Agnico-Eagle expects to have a feasibility study completed by the end of
the first quarter of 2006. The study will then undergo an independent review
and will be presented to Agnico-Eagle's board for consideration in the second
quarter of 2006.
Currently, a 3,000 tonnes per day mining operation is being contemplated
using both open pit and underground mining methods. Initially, the operation
would be an open pit operation phasing into an underground mine as the deeper
reserves are developed and the deeper resource explored and converted. Based
on the current probable reserves, and the proposed mining rate of 1.0 million
tonnes per year, the project has a potential mine life of over 10 years.
Currently, capital expenditures have been estimated to be approximately
$170 million. The mineralization is refractory and pressure oxidation has been
selected as the process to extract the gold. Gold recoveries have been
confirmed to be in the 87% to 90% range.
Suurikuusikko will be subject to a large scale underground exploration
drilling program from a ramp as soon as possible. This will determine the
ultimate size of the gold system, and is an important component of the
development work proposed in the feasibility study. While the ramp would
initially be used to convert resources to reserves and explore the structure,
it will also be used for underground production. This program is included in
the $170 million capital expenditure program which is being contemplated.
The property is fully permitted, having environmental, mining and water
permits. The environmental permit is currently being amended to reflect the
proposed change in treatment process.
Finland has a mining history and supplies some of the world's best
processing and mining equipment. The Federal and regional governmental
agencies have been and are highly supportive of the project. The property is
close to infrastructure, including hydro power, a major airport, the
municipality of Kittila, and mining and construction contractors. The project
also has access to a highly qualified labour force.
Managing Director, Europe Appointed
Agnico-Eagle is pleased to announce the appointment of Mr. Ingmar Haga as
Managing Director, Europe. Mr. Haga will be responsible for all of Agnico-
Eagle's European mining activities. Mr. Haga has over 30 years of experience
in the mining industry, including 21 years with Outokumpu Mines Inc. of
Finland, most recently as Vice President, Business Development.
Mr. Haga will replace Mr. Lars-Goran Ohlsson, the former Riddarhyttan
Managing Director and CEO, who has announced his retirement. Mr. Ohlsson was
instrumental in advancing the property from its infancy to its present state.
Agnico-Eagle is pleased to announce that Mr. Ohlsson will remain involved with
the Company in a consulting capacity.
Forward Looking Statements
Certain of the foregoing statements are based on preliminary views of the
Company with respect to such matters as, among other things, grade, tonnage,
processing, mining methods and location of surface infrastructure and actual
results and final decisions may be quite different.
The information in this press release has been prepared as at
February 20, 2006. Certain statements contained in this press release
constitute "forward-looking statements" within the meaning of the United
States Private Securities Litigation Reform Act of 1995. When used in this
document, the words "anticipate", "expect", "estimate," "forecast," "planned"
and similar expressions are intended to identify forward-looking statements.
Such statements reflect the Company's views at the time with respect to future
events and are subject to certain risks, uncertainties and assumptions. Many
factors could cause the actual results to be materially different from those
expressed or implied by such forward-looking statements, including, among
others, those which are discussed under the heading "Risk Factors" in the
Company's most recently filed Annual Information Form and Annual Report on
Form 20-F. The Company does not intend, and does not assume any obligation, to
update these forward-looking statements.
About Agnico-Eagle
Agnico-Eagle is a long established Canadian gold producer with operations
located in Quebec and exploration and development activities in Canada,
Finland, the United States and Mexico. Agnico-Eagle's LaRonde Mine is Canada's
largest gold deposit. The Company has full exposure to higher gold prices
consistent with its policy of no forward gold sales. It has paid a cash
dividend for 26 consecutive years.
Detailed Mineral Reserve and Resource Data
Cautionary Note to U.S. investors concerning estimates of Measured and
Indicated Resources. This section uses the terms "measured" and "indicated
resources." We advise U.S. investors that while those terms are recognized and
required by Canadian regulations, the U.S. Securities and Exchange Commission
does not recognize them. U.S. investors are cautioned not to assume that any
part or all of mineral deposits in these categories will ever be converted
into reserves. Cautionary Note to U.S. investors concerning estimates of
Inferred Resources. This section also uses the term "inferred resources." We
advise U.S. investors that while this term is recognized and required by
Canadian regulations, the U.S. Securities and Exchange Commission does not
recognize it. "Inferred resources" have a great amount of uncertainty as to
their existence, and great uncertainty as to their economic and legal
feasibility. It cannot be assumed that all or any part of an Inferred Mineral
Resource will ever be upgraded to a higher category. Under Canadian rules,
estimates of Inferred Mineral Resources may not form the basis of feasibility
or pre-feasibility studies, except in rare cases. U.S. investors are cautioned
not to assume that part or all of an inferred resource exists, or is
economically or legally minable.
-------------------------------------------------------------------------
Gold Grade Contained Gold Tonnes
Probable Mineral Reserve (g/t) (000's oz.) (000's)
-------------------------------------------------------------------------
Open Pit 4.97 623 3,900
-------------------------------------------------------------------------
Underground 5.37 1,702 9,857
-------------------------------------------------------------------------
Total Probable Mineral Reserve 5.26 2,325 13,757
-------------------------------------------------------------------------
-------------------------------------------------------------------------
Gold Grade Contained Gold Tonnes
Measured Mineral Resource (g/t) (000's oz.) (000's)
-------------------------------------------------------------------------
Open Pit 1.49 1 16
-------------------------------------------------------------------------
Underground 4.11 18 139
-------------------------------------------------------------------------
Total Measured Mineral Resource 3.84 19 155
-------------------------------------------------------------------------
-------------------------------------------------------------------------
Gold Grade Contained Gold Tonnes
Indicated Mineral Resource (g/t) (000's oz.) (000's)
-------------------------------------------------------------------------
Open Pit 1.44 4 82
-------------------------------------------------------------------------
Underground 4.37 229 1,633
-------------------------------------------------------------------------
Total Indicated Resource 4.23 233 1,715
-------------------------------------------------------------------------
-------------------------------------------------------------------------
Gold Grade Contained Gold Tonnes
Inferred Mineral Resource (g/t) (000's oz.) (000's)
-------------------------------------------------------------------------
Underground 4.35 934 6,688
-------------------------------------------------------------------------
Total Inferred Resource 4.35 934 6,688
-------------------------------------------------------------------------
Tonnage amounts and contained metal amounts presented in the tables in
this news release have been rounded to the nearest 1000.
Scientific and Technical Data
The exploration results disclosed in this press release were reviewed by
Normand Bédard, P.Geo. Abitibi Regional Division's Senior Geologist. The
drilling, sampling and assaying procedures, the verification procedures, the
quality assurance program and quality control procedures used in preparing
such data may be found in the Independent Technical Report on Riddarhyttan
Resources AB prepared by SRK Consulting (Canada) Inc. and dated November 15,
2005 that is filed on SEDAR.
Agnico-Eagle Mines Limited is reporting mineral resource and reserve
estimates in accordance with the CIM guidelines for the estimation,
classification and reporting of resources and reserves. Cautionary Note to
U.S. Investors-The United States Securities and Exchange Commission permits
U.S. mining companies, in their filings with the SEC, to disclose only those
mineral deposits that a company can economically and legally extract or
produce. We use certain terms in this press release, such as "measured,"
"indicated," and "inferred," "resources," that the SEC guidelines strictly
prohibit U.S. registered companies from including in their filings with the
SEC. U.S. Investors are urged to consider closely the disclosure in our Form
20-F, which may be secured from us, or from the SEC's website at:
http://sec.gov/edgar.shtml. A "final" or "bankable" feasibility study is
required to meet the requirements to designate reserves under Guide 7.
Estimates were calculated using historic three-year average metals prices and
foreign exchange rates in accordance with the SEC Industry Guide 7. Industry
Guide 7 requires the use of prices that reflect current economic conditions at
the time of reserve determination which Staff of the SEC has interpreted to
mean historic three-year average prices. The assumptions used for 2005
reserves and resources were $405 per ounce gold. There are no known relevant
issues that would materially affect the estimate. No independent verification
of the data has been published.
The Qualified Person responsible for the Suurikuusikko mineral resource
and mineral reserve estimate is Normand Bédard P.Geo. Abitibi Regional
Division's Senior Geologist. The effective date of the estimate is
February 20th 2006. A technical report describing the mineral resource and
mineral reserve estimate will be filed with the securities regulatory
authorities in due course.
Wireframe models of zones comprising the Suurikuusikko deposit that were
used to estimate the mineral resource were derived using drill hole
intercepts. The key assumptions used to determine the drill hole intercept
intervals were a gold price of $405 per ounce, metallurgical recoveries of 87%
for gold, and cut-off grades that varied were applied depending on whether the
material could be potentially mined by open pit or by underground methods.
Gold assays were cut to 50 grams per tonne. For the open pit resource models,
a minimum gold grade cut-off of 1.0 grams per tonne was used to evaluate drill
hole intercepts that have been adjusted to respect a minimum mining width of
3.0 metres (horizontal width). For the underground resource models, a minimum
gold grade cut-off of 3.0 grams per tonne was used to evaluate drill hole
intercepts that have been adjusted to respect a minimum mining width of 3.0
metres (horizontal width).
The mineral resource estimate was derived using a three dimensional block
model of the deposit; the grades were interpolated using the inverse distance
power squared method. In order to estimate the mineral reserve, a dilution
factor was applied between 10 and 20 percent depending on the mining method.
For the open pit reserve models, a minimum gold grade cut-off of 1.7 grams per
tonne was used. For the underground reserve models, a minimum gold grade cut-
off of 4.0 grams per tonne was used.
Canadian Administrator's National Instrument 43-101 requires mining
companies to disclose reserves and resources using the subcategories of
"proven" reserves, "probable" reserves, "measured" resources, "indicated"
resources and "inferred" resources. Mineral resources that are not mineral
reserves do not have demonstrated economic viability.
A mineral reserve is the economically mineable part of a measured or
indicated resource demonstrated by at least a preliminary feasibility study.
This study must include adequate information on mining, processing,
metallurgical, economic and other relevant factors that demonstrate, at the
time of reporting, that economic extraction can be justified. A mineral
reserve includes diluting materials and allows for losses that may occur when
the material is mined. A proven mineral reserve is the economically mineable
part of a measured resource for which quantity, grade or quality, densities,
shape and physical characteristics are so well established that they can be
estimated with confidence sufficient to allow the appropriate application of
technical and economic parameters, to support production planning and
evaluation of the economic viability of the deposit. A probable mineral
reserve is the economically mineable part of an indicated mineral resource for
which quantity, grade or quality, densities, shape and physical
characteristics can be estimated with a level of confidence sufficient to
allow the appropriate application of technical and economic parameters, to
support mine planning and evaluation of the economic viability of the deposit.
A mineral resource is a concentration or occurrence of natural, solid,
inorganic or fossilized organic material in or on the earth's crust in such
form and quantity and of such a grade or quality that it has reasonable
prospects for economic extraction. The location, quantity, grade, geological
characteristics and continuity of a mineral resource are known, estimated or
interpreted from specific geological evidence and knowledge. A measured
mineral resource is that part of a mineral resource for which quantity, grade
or quality, densities, shape, physical characteristics, can be estimated with
a level of confidence sufficient to allow the appropriate application of
technical and economic parameters, to support mine planning and evaluation of
the economic viability of the deposit. The estimate is based on detailed and
reliable exploration, sampling and testing information gathered through
appropriate techniques from locations such as outcrops, trenches, pits,
workings and drill holes that are spaced closely enough to confirm both
geological and grade continuity. An indicated mineral resource is that part of
a mineral resource for which quantity, grade or quality, densities, shape and
physical characteristics can be estimated with a level of confidence
sufficient to allow the appropriate application of technical and economic
parameters, to support mine planning and evaluation of the economic viability
of the deposit. The estimate is based on detailed and reliable exploration and
testing information gathered through appropriate techniques from locations
such as outcrops, trenches, pits, workings and drill holes that are spaced
closely enough for geological and grade continuity to be reasonably assumed.
An inferred mineral resource is that part of a mineral resource for which
quantity and grade or quality can be estimated on the basis of geological
evidence and limited sampling and reasonably assumed, but not verified,
geological and grade continuity. The estimate is based on limited information
and sampling gathered through appropriate techniques from locations such as
outcrops, trenches, pits, workings and drill holes. Mineral resources which
are not mineral reserves do not have demonstrated economic viability.
Investors are cautioned not to assume that part or all of an inferred
resource exists, or is economically or legally mineable.
>>
For further information: David Smith, Director, Investor Relations,
(416) 947-1212
For further information: David Smith, Director, Investor Relations, (416) 947-1212