TORONTO, Oct. 28 /CNW-PRN/ - Agnico-Eagle Mines Limited today reported a net loss of US$5.1 million, or US$0.09 per share for the quarter ended September 30, 1999 compared to a net loss of US$2.5 million, or US$0.05 per share in the same period last year. Operating cash flow declined in the third quarter to a deficit of US$5.5 million, or US$0.10 per share, compared to cash flow of US$0.2 million, or nil per share in the 1998 third quarter. Earnings and cash flows were weaker than in 1998 due to 20-year low gold prices, decreased gold production due to the mining of lower grade gold ore from the nearly depleted mining areas of Shafts No. 1 and No. 2 and the settlement of the lawsuit with Noranda Inc. for C$1.9 million (US$1.3 million). These factors were partially offset by a continued improvement in mine operating cost performance with operating costs per ton declining 13 percent to C$53 per ton.
``The third quarter was characterized by very difficult operating conditions in the few remaining mining blocks at Shafts No. 1 and No. 2 along with steady progress on the soon to be completed development and expansion program at our new Shaft No. 3,'' said Sean Boyd, Agnico-Eagle's President and Chief Executive Officer. ``In addition, since our last drilling update on October 14, new drill results from Shaft No. 3 continue to confirm thicker mineralization and higher grades than previously indicated,'' added Mr. Boyd.
Operating Results
Onsite operating costs improved in the second quarter to C$53 per ton of ore milled compared to C$61 per ton in same quarter of 1998. However, gold production was substantially lower at 15,024 ounces due to a combination of factors including difficult mining conditions and lower gold grades at Shaft No. 1, and the commissioning of the new 5000 ton per day SAG mill in August which resulted in two weeks of downtime in the mill.
As a result, the year to date cash operating costs to produce an ounce of gold increased to US$256 per ounce from US$214 per ounce as gold production decreased to 73,824 ounces from 113,387 ounces in 1998. On a quarterly basis, cash costs per ounce in the third quarter were abnormally high at US$375. The average gold price realized to date in 1999 is US$273 per ounce, down eight percent from US$296 per ounce realized in 1998. For the year to date, the net loss was US$9.7 million, or US$0.18 per share compared to US$6.6 million, or US$0.14 per share in 1998.
Fourth quarter operating results are expected to improve as the new SAG mill will be operational for the full quarter and more ore will be processed from the new mining areas at Shaft No. 3 including the first mining block from Zone 20 South - El Coco. In addition, the daily mining rate will reach 3,600 tons per day by December compared to the average daily throughput in the third quarter of approximately 2,000 tons per day.
Financial Position
At September 30, 1999 Agnico-Eagle's financial position remained strong with a cash balance of US$35 million and a working capital position of US$39 million. In August, the Company announced that a US$100 million 8-year bank facility had been fully underwritten with Deutsche Bank AG and Barclays Bank PLC. Since that time, the facility has been successfully syndicated to a number of other banks including The Bank of Nova Scotia, Standard Bank London Limited, Dresdner Bank Kleinwort Benson and CIBC World Markets. The credit facility is expected to close by the middle of November, as scheduled.
As part of this credit facility, the Company is required to put in place downside price protection for gold in the form of put options on approximately 20% of its total current gold reserves and resources. The cost of purchasing these put options will be financed, in part, by selling call options on a small percentage of the Company's by-product metal reserves. Consistent with its policy of the last 20 years, the Company will not sell away any of the upside on its future gold production.
The Company plans to spend US$89 million to the end of 2002 to complete its ongoing expansion program. Of this amount, US$24 million is expected to be spent in the last quarter of 1999, US$44 million in 2000, US$17 million in 2001 and US$4 million in 2002. The Company's cash and bullion balance, along with projected cash flows from operations over this period are expected to be sufficient to cover the remaining US$89 million investment required to achieve a production rate of 5000 tons per day. The bank facility is intended to provide the working capital required during the early years of the capital expenditure program and to enhance Agnico-Eagle's liquidity and financial flexibility.
Laronde Exploration Program
Since our last exploration update on October 14, additional drill results have been received from the definition drilling programs on Zone 20 South and Zone 20 North. These results continue to identify higher grade gold mineralization and thicker mining widths than expected. A total of six drills are currently working underground at LaRonde.
Zone 20 South - El Coco
The 20 South - El Coco underground drill program continues to confirm higher grade mineralization within the known resource outline as well as extending the known area of mineralization. Two new drill holes have been completed within the present resource outline over the past two weeks. The following results were obtained:
----------------------------------------------------------------------
True Gold(oz/ton) Silver
Drill Hole Thickness (ft.) Cut (1.5 oz) (oz/ton) Copper(%) Zinc(%)
-----------------------------------------------------------------------
3122-32 10.5 0.16 0.98 0.08 3.84
-----------------------------------------------------------------------
3122-33 26.9 0.58 3.76 0.39 6.05
-----------------------------------------------------------------------
Uncut 26.9 0.95 3.76 0.39 6.05
-----------------------------------------------------------------------
In addition, drill holes were completed outside of the known Zone 20 South resource outline. Two drill holes intersected Zone 20 South at depth while one continued to extend the zone upward. The following values were intersected:
True Gold (oz/ton) Silver
Drill Hole Thickness (ft.) Cut (1.5 oz) (oz/ton) Copper(%) Zinc(%)
20-293 10.2 0.09 2.66 0.10 5.72
3134-77 11.5 0.15 1.42 1.10 2.04
3134-78 9.2 0.33 1.05 0.46 2.09
In addition to another high grade gold intersection within the known mineralized zone (hole 3122-33), drilling has now extended Zone 20 South down to the Level 146 horizon (4,700 feet below surface). Furthermore, there are also indications that Zone 20 South may extend up to the 20th Level drift (2,800 feet below surface). Development on the 20th Level exploration drift is in progress to provide drill platforms to conduct additional drilling. Four drills are currently drilling Zone 20 South, the first on the 20th Level exploration drift (testing the upward extension), the second on Level 122 continuing the definition drilling program, the third on Level 134 continuing to confirm the downward extension and the fourth on Level 146 testing for further depth potential.
A surface exploration program has also begun on the El Coco property and the Company's Sphinx property immediately to the east of El Coco. A recently completed geophysical survey of both properties has identified several targets that will be drill tested beginning in mid- November. This work will assist the Company in identifying specific target areas for the extensive underground drifting and drilling program that will begin across El Coco and Sphinx by the middle of next year.
Zone 20 North
The Zone 20 North definition drill program continues to return positive results from Levels 134 and 194 at Shaft No. 3. On Level 194 drill hole 3194-05 returned the following results:
------------------------------------------------------------------------
True Gold(oz/ton) Silver
Drill Hole Thickness (ft.) Cut (1.5 oz) (oz/ton) Copper(%) Zinc(%)
------------------------------------------------------------------------
3194-05-Au 44.3 0.19 1.83 1.46 0.53
------------------------------------------------------------------------
-Zn 9.2 0.01 0.63 0.09 8.32
------------------------------------------------------------------------
The drill hole intersected Zone 20 North at the currently known western limit and was approximately 350 feet west of an earlier reported hole (3194-04) which returned 0.36 ounces of gold per ton and 5.55 ounces of silver with copper and zinc mineralization over a true thickness of 42 feet. Definition drilling along Level 194 has now indicated a Zone 20 North strike length of 1,500 feet compared to a previously estimated strike length in this area of 750 feet. Zone 20 North remains open for expansion along strike to the east and west.
A drill is currently being set up on Level 206 (approximately 400 feet) below Level 194 to test the downward extension of the higher grade gold mineralization encountered on Level 194. This will be followed by drilling from Level 215. The company anticipates having both the Level 206 and Level 215 drilling completed by the end of 1999.
From Level 134 the program to define the western limit on the upper portion of Zone 20 North continued. The following result was obtained:
------------------------------------------------------------------------
True Gold(oz/ton) Silver
Drill Hole Thickness (ft.) Cut (1.5 oz) (oz/ton) Copper(%) Zinc(%)
------------------------------------------------------------------------
3134-76-Au 36.1 0.16 1.24 0.28 0.04
------------------------------------------------------------------------
-Zn 53.0 0.03 5.81 0.06 10.90
------------------------------------------------------------------------
This result continues the confirmation of increased mineralized thickness and higher gold grades in an area where we had previously encountered primarily zinc/silver mineralization. Both the Level 134 and 194 drilling results continue to confirm that Zone 20 North gold mineralization is more extensive than originally thought.
With the completion of the Level 194 definition drilling program, the drill on this level has resumed the deep drilling program on Zone 20 North. The drill has completed 200 feet of its planned 3,000 foot length. The target of this drill hole is approximately 8,800 feet below surface between the recently reported deep intersection on Zone 20 North at 9,700 feet below surface and an earlier drill intersection at 7,400 feet below surface. Each of these drill holes intersected massive sulfide mineralization over true thicknesses of approximately 50 feet containing gold, silver, copper and zinc. Results of the current deep drill hole are anticipated prior to the release of the updated reserve and resource calculation in February 2000.
The Longitudinal illustrations that detail the drill results presented in this news release and an earlier release on October 14 can be viewed and/or downloaded from the Company's website:
www.agnico-eagle.com (Press Release) or
LaRonde Expansion Program
Shaft Sinking and Mill Expansion
Shaft No. 3 is currently at a depth of 6,950 feet and ground conditions continue to be excellent. Shaft sinking remains on schedule with 400 feet remaining to be completed by the middle of February 2000. Underground infrastructure completed during the quarter included the main pumping station on Level 122, the 5,000 ton ore bin, truck dump and waste pass rock breaker on Level 146 and completion of the paste backfill lines down to the 188 sublevel horizon. In addition, the main upcast and downcast ventilation fans are nearing completion and the chute and conveyor installations are currently underway on Level 152. Underground development continues to progress on budget with 20,000 feet completed to the end of the third quarter.
The 5,000 ton per day SAG mill was placed into operation in early August and was fully commissioned by the end of the month. Significant progress was made on the paste backfill plant with the erection of structural steel and commencement of equipment installation. The design of the precious metals recovery circuit has been completed, foundation contracts have been awarded and construction has commenced. This facility is scheduled to be completed by the end of third quarter 2000 at which time the Company will be in a position to process the planned 5,000 tons of ore per day.
Year 2000
The Company is fully aware of the potential disruption that may be caused by the passage to the Year 2000 and other data-related problems associated with it.
The primary concern has been the financial systems used by Agnico-Eagle. The Company's critical systems have been confirmed by our vendors to be Year 2000 compliant. These systems are currently being upgraded to the most recent versions that are confirmed to be compliant.
The inventory of equipment and instrumentation used in Agnico-Eagle's mine operations has been completed. Testing of these systems and contacting of customers and suppliers to confirm compliance has been completed for critical process control equipment. Moreover, third party suppliers have been requested to warrant compliance of date sensitive instrumentation as a condition attached to any purchase order issued for such instrumentation.
Based on the Company's current assessment, Agnico-Eagle has determined that its mission critical systems are already Year 2000 compliant and major systems modification is not expected. Therefore, costs to complete this process are not expected to be material.
Favourable responses have been received from critical third party suppliers and financial institutions regarding their preparedness for the transition to the Year 2000. Reliability of the commitments or comfort that will be expressed has been evaluated and a contingency plan has been defined where either criticality or insufficient comfort warrants it. This has equally been the case for financial systems and mine operation equipment and instrumentation.
The time frames during which the Company believes it will complete its Year 2000 modifications and the cost estimates to complete these modifications are based on management's best estimates, which were made in reliance on numerous assumptions of future events, including the continued availability of certain resources and other factors. Any change in these assumptions may affect projections made by the Company. There can be no guarantee that the estimated costs will be achieved; actual results could differ materially from those anticipated.
This press release contains certain ``forward-looking statements'' (within the meaning of the United States Private Securities Litigation Reform Act of 1995) that involve a number of risks and uncertainties. There can be no assurance that such statements will prove to be accurate; actual results and future events could differ materially from those anticipated in such statements. Other risks and uncertainties are disclosed under the heading ``Risk Factors'' in the Company's Annual Information Form (AIF) filed with certain Canadian securities regulators (including the Ontario and Quebec Securities Commissions) and with the United States Securities and Exchange Commission (as Form 20-F).
Agnico-Eagle Mines Limited is an established Canadian gold producer with operations located principally in northwestern Quebec and exploration and development activities in Quebec, Ontario and Nevada. Consistently one of the industry's lowest-cost producers, Agnico's operating history includes 24 years of continuous gold production primarily from underground mining operations. Current proven and probable gold reserves stand at 1.5 million contained ounces, with an additional 3.5 million ounces in the mineral resource category at its LaRonde Mine. Agnico-Eagle is currently focused on the expansion and large scale exploration program of its LaRonde Mine which is expected to result in increased gold production and expanded gold reserves.
Summarized Quarterly Data Agnico-Eagle Mines Limited
(Unaudited)
(thousands of United States Three months ended Nine months ended
dollars, except per share and September 30, September 30,
per ounce amounts) (Note 1) 1999 1998 1999 1998
Consolidated Financial Data
Income and cash flow
Revenues from mining
operations (Note 2) $ 5,557 $ 10,293 $ 22,873 $ 32,004
Net loss for period $ (5,063) $ (2,533) $ (9,698) $ (6,622)
Loss per share $ (0.09) $ (0.05) $ (0.18) $ (0.14)
Operating cash flow (Note 3) $ (5,500) $ 237 $ (7,100) $ 537
Operating cash flow per share $ (0.10) $ 0.00 $ (0.13) $ 0.01
Gold production-ounces 15,024 37,075 73,824 113,387
Average gold price - per ounce
realized $ 263 $ 292 $ 273 $ 296
Average exchange rate - US$
per Canadian dollar 0.6731 0.6607 0.6708 0.6841
Weighted average number of
shares - basic (in thousands) 53,257 53,017 53,345 48,853
Operating and Financial Summary
LaRonde Division
Revenues from mining operations
(Note 2) $ 5,557 $ 10,293 $ 22,873 $ 32,004
Mine operating costs 6,542 8,289 21,950 25,681
-------------------------------------------------------------------------
Mine operating profit (loss) $ (985) $ 2,004 $ 923 $ 6,323
-------------------------------------------------------------------------
----------------------------------------
Tons of ore milled 182,992 207,262 570,570 588,071
Grade - ounces of gold per ton 0.09 0.19 0.14 0.21
Gold production - ounces 15,024 37,075 73,824 113,387
Silver production - ounces 49,493 53,459 194,666 217,216
Copper production - pounds 603,486 1,677,246 2,806,810 4,624,208
Zinc production - pounds 1,302,825 190,052 4,650,620 190,052
Onsite operating costs per
ton milled (Canadian dollars) $ 53 $ 61 $ 57 $ 65
-------------------------------------------------------------------------
----------------------------------------
Operating costs per gold ounce
produced (US$):
Onsite operating costs
(including reclamation
provision) $ 431 $ 226 $ 296 $ 229
Less: Non cash reclamation
provision (4) (3) (4) (3)
Net by-product revenues (52) (9) (36) (12)
-------------------------------------------------------------------------
Cash operating costs $ 375 $ 214 $ 256 $ 214
Non cash costs:
Reclamation provision 4 3 4 3
Depreciation and amortization 103 34 58 43
-------------------------------------------------------------------------
Total operating costs $ 482 $ 251 $ 318 $ 260
-------------------------------------------------------------------------
----------------------------------------
Notes to Summarized Quarterly Data and Consolidated Financial
Statements:
(1) Effective January 1, 1999, Agnico-Eagle changed its functional and
reporting currency from Canadian to United States dollars. The
temporal method is applied for the accounting currency transactions and
translation. Comparative figures for periods prior to January 1, 1999,
denominated into Canadian dollars, are translated into United States
dollars, under generally accepted Canadian accounting principles, using
the closing spot Canadian and United States currency exchange rate as
at December 31, 1998 of $1.5333.
(2) Revenues from mining operations consists of gold and by product
revenues net of smelting and refining charges.
(3) Before non-cash working capital adjustments.
Consolidated Balance Sheets Agnico-Eagle Mines Limited
-------------------------------------------------------------------------
(thousands of United States dollars) September 30, December 31,
1999 1998
-------------------------------------------------------------------------
(Unaudited)
ASSETS
Current
Cash and cash equivalents $ 34,851 $ 76,262
Metals awaiting settlement and gold bullion 4,828 23,210
Income taxes recoverable 746 714
Prepaid expenses, supplies and other 9,188 6,558
-------------------------------------------------------------------------
Total current assets 49,613 106,744
-------------------------------------------------------------------------
Investments, loans, advances and other assets 11,796 13,560
Future income and mining tax assets 7,398 4,061
Mining properties 202,676 156,388
-------------------------------------------------------------------------
$ 271,483 $ 280,753
-------------------------------------------------------------------------
-------------------------
LIABILITIES AND SHAREHOLDERS' EQUITY
Current
Accounts payable and accrued liabilities $ 6,886 $ 6,832
Dividends payable 638 1,660
Income and mining taxes payable 2,649 2,885
Current interest due on senior convertible notes 789 1,897
-------------------------------------------------------------------------
Total current liabilities 10,962 13,274
-------------------------------------------------------------------------
Senior convertible notes 108,141 105,239
-------------------------------------------------------------------------
Reclamation provision and other liabilities 5,016 4,507
-------------------------------------------------------------------------
Future income and mining tax liabilities 8,258 9,695
-------------------------------------------------------------------------
Minority interest 3,287 3,592
-------------------------------------------------------------------------
Shareholders' Equity
Common shares
Authorized - unlimited
Issued - 55,288,708 (1998 - 55,112,625) 152,378 151,307
Other paid in capital 14,535 14,535
Contributed surplus 3,886 3,886
Deficit (21,197) (11,499)
Company's own shares held by a subsidiary company (13,783) (13,783)
-------------------------------------------------------------------------
Total shareholders' equity 135,819 144,446
-------------------------------------------------------------------------
$ 271,483 $ 280,753
-------------------------------------------------------------------------
----------------------------
Consolidated Statements of Loss Agnico-Eagle Mines Limited
(Unaudited)
-------------------------------------------------------------------------
(thousands of United Three months ended Nine months ended
States dollars, except September 30, September 30,
per share amounts) 1999 1998 1999 1998
-------------------------------------------------------------------------
REVENUES
Revenues from mining operations $ 5,557 $ 10,293 $ 22,873 $ 32,004
Interest and sundry income 561 1,249 2,293 2,830
-------------------------------------------------------------------------
6,118 11,542 25,166 34,834
COSTS AND EXPENSES
Production 6,700 8,595 22,233 25,681
Exploration 688 456 2,051 1,614
Depreciation and amortization 1,553 1,240 4,262 4,649
General and administrative 877 868 2,988 2,586
Capital tax 227 375 765 933
Interest 2,166 2,228 6,467 6,432
Other 970 - 970 -
-------------------------------------------------------------------------
Loss before the undernoted (7,063) (2,220) (14,570) (7,061)
Foreign currency gain (loss) (1,108) (652) 703 (1,164)
-------------------------------------------------------------------------
Loss before income and mining
tax recoveries (8,171) (2,872) (13,867) (8,225)
Income and mining tax recoveries (3,108) (339) (4,169) (1,603)
-------------------------------------------------------------------------
Net loss for the period $ (5,063) $ (2,533) $ (9,698) $ (6,622)
-------------------------------------------------------------------------
----------------------------------------
Loss per share $ (0.09) $ (0.05) $ (0.18) $ (0.14)
-------------------------------------------------------------------------
Consolidated Statements of Cash Flows Agnico-Eagle Mines Limited
(Unaudited)
-------------------------------------------------------------------------
(thousands of United States Three months ended Nine months ended
dollars) September 30, September 30,
1999 1998 1999 1998
-------------------------------------------------------------------------
Operating activities
Net loss for the period $ (5,063) $ (2,533) $ (9,698) $ (6,622)
Add (deduct) items not affecting
cash from operating activities:
Depreciation and amortization 1,553 1,240 4,262 4,649
Future provision of income and
mining recoveries (3,255) (497) (4,640) (2,062)
Foreign currency translation loss 959 545 135 1,082
Amortization of deferred interest
and financing costs on senior
convertible notes 1,073 1,014 3,139 2,894
Other (767) 468 (298) 596
-------------------------------------------------------------------------
(5,500) 237 (7,100) 537
Net change in non-cash working
capital balances related to
operations
Metals awaiting settlement and
gold bullion 13,573 1,808 18,382 2,358
Prepaid expenses, supplies and
other (3,144) (1,617) (2,630) (191)
Income and mining taxes
recoverable and payable (72) 371 (268) 568
Accounts payable and accrued
liabilities 2,695 831 362 124
Current interest due on senior
convertible notes (1,107) (1,025) (1,108) (980)
-------------------------------------------------------------------------
Cash flows from operating
activities 6,445 605 7,638 2,416
-------------------------------------------------------------------------
Investing activities
Additions to mining properties (15,478) (12,6