Goldex

Val-d’Or, Quebec

The Goldex mine is part of the chain of operations and properties that Agnico Eagle owns in the Abitibi region of northwestern Quebec. Underground mining from the M and E satellite zones and processing in the mill started in September 2013. Commercial production was achieved in October 2013. The Deep 1 project was declared to be in commercial production in July 2017.

Key Facts

Mine Type

Underground

2016 production

Production - 120,704 oz gold

2016 costs

Production costs - $525/oz gold

Total cash costs - $532/oz gold

Gold reserves

886,000 oz

Mine life

9 years

Mine Production

2016 Output

Quarterly Gold Production

Employees

316